phase1 - Fundraising and Purchase
phase2 - Accessibility, Safety, Infrastructure repairs
phase3a - Habitability: Kitchen installation, CH Vestibule rebuilding
phase3b - Habitability: Plaster, Painting, Lighting upgrades, Ventilation
(still to be done)
phase 4 - Upkeep: Exterior repairs and painting, Horticulture Plan
(still to be done)
plan
The church building in the center of the hamlet of New Concord was owned and used by the Dutch Reformed church for many years. When the Dutch Reformed Classis discontinued its use as a place of worship, the structure's future became uncertain. The Society of New Concord stepped in and committed to the purchase and preservation of the building.
Phase 1
Fundraising and Purchase (already accomplished)
The fund-raising effort to save the church had huge local participation: each member of the Society Executive Committee pledged and contributed [100% participation, 24 % of funds raised]; all members of the Fund-raising Committee pledged [100% participation, 14% of funds raised]; and there was 46% participation from our members at large. We also managed contributions from local businesses [2% of funds raised].
Although purchase was complicated by two NY State liens on the property (old heating oil-spill cleanup), the sale closed in October, 2011; the whole acquisition lasted about two-and-a-half years. The first feelers about disposing of the buildings came in early Spring 2009, and we eventually negotiated with the Classis of Columbia-Greene Reformed Church (owners of the property), and the NY State Attorney General’s Office (holder of the liens). There were also eventually settlements about an easement for the boundary between the church property and the (Muth) house to the north, and hearings before the Zoning Board of Appeals (potential “change of use”). Bringing about the sale was a long and intense behind-the-scenes process.
Phase 2
Accessibility, Safety, Infrastructure repairs (already accomplished)
In a series of “barn raising” events during 2013, we used crews of volunteer neighbors—under the direction of professional contractors—to accomplish:
Demolition weekend [29 participants, February 2-3, 2013]: removal of waterlogged flooring and rotted sub-flooring, of all vertical sheetrock, of damaged partitions and kitchen cabinets, interior doors and bathroom fixtures.
Reconfiguring and Framing Rooms
Insulation Installation [12 participants, April 13, 2013]; placement of vapor barrier and fiberglass insulation all exterior walls and selected interior walls
New Windows Campaign [13 individuals or couples, first week of May, 2013]; fundraising to purchase 11 new double-pane windows
Sheet Rocking Weekend [12 participants, June 2-3, 2013]; many of us learned how to install sheetrock: all interior and exterior walls
Interior Painting [6 participants, June and July, 2013]; painting walls, window trim, doors and casings
Doors and Floors [carpenters and technician, Fall 2013]; installation of hardwood floors, new interior doors and door hardware
We also completed the following during the course of 2012-2016:
Solicitation of grants and donations for materials and repairs
Building Cleanup, rodent extermination [both buildings inside and outside]
Rebuilding of cornice returns [Community Hall], eaten by animals
Cleaning of chimney, installation of flue cap, reconditioning oil burner [Community Hall]
Complete re-plumbing of the building [Community Hall]
Complete rewiring both buildings: new breaker boxes, metal shielded cables, switches, outlets and LED lights, compliant with modern building/safety codes
Creating passageway between two buildings to allow wheelchair access to all public spaces
Completing handicap-accessible bathroom: sink, toilet, exhaust fan, water heater, grab bars, mirror, and pressure tank
Installing 2 fire extinguishers in each building, smoke and CO detectors, emergency lighting and exit signs
Making new emergency/accessible entrance with wheelchair ramp
Obtaining and installing period-appropriate box lock (with modern cylinder), repairing main double doors [Meeting House]
Replacing cracked tiles of slate roof, shortening and repairing brick chimney, placing new copper chimney flashing, installing new copper roof ridge cap, Meeting House [June 2014]
Restoration and reinstallation of all the stained-glass windows [Meeting House], thanks to a grant from the Veillette-Nifosi foundation [total project completion, April 2015]
Community Hall Ceiling repair, new LED light panels and sound-control baffles [Summer 2015]
Acquiring cabinets and appliances from a Long Island kitchen renovation, to be fitted into our “kitchen” room
Acquiring a good-quality used refrigerator [Community Hall]
Securing a pledge for a 5-year lease to the adjacent land parcel, along with a grant for clearing and grading into a picnic grove (informal permission accomplished, legal lease pending)
Removing two mature maple trees in front of Meeting House obscuring facade and impinging on roof and bell tower [September 2015]
Phase 3a
Habitability: Kitchen installation, CH Vestibule rebuilding, Roof (already accomplished)
These items were required to make the buildings more useful and comfortable:
Install kitchen cabinets and appliances; refurbish Corian countertops and install granite work surface. New under-counter LED lighting; rewire and fit range hood
Replace controller circuit board, double wall ovens
Construction of rolling bar/serving table (from leftover base cabinets)
Rebuild/renovation of Community Hall entry vestibule:
gut demolition of interior
rebuild floor on concrete footings
reframe closets; sheetrock; casings and chair rails
new double entry door unit and closet windows (existing too rotted and narrow for handicap accessibility)
complete rewiring of vestibule
ceramic tile floor
interior lighting
new stone steps and railings
Repair/replacement septic tank and drainage system
Outdoor lighting (safety), steps, parking area, Meeting House facade
Removal of 3 trees (2 maple, 1 elm) threatening buildings (May 2019)
Replace Community Hall Roof (July 2019)
Phase 3b
Habitability: Plaster repair, Painting, Lighting upgrades, Ventilation (already accomplished)
Repair/replaster MH ceiling by thin sheet rock lamination and hand plastering [now that leaking roof and chimney have been fixed] finished February 2020.
Remove old chimney thimble Meeting House interior north wall [2 participants, January 2020]
Chip, scrape, patch, prime and paint interior walls, Meeting House [crew of 6 neighbors, finished March 2020]
Repair and reinstall pews [7 neighbors, finished June 2021]
Repaint walls and trim, Community Hall [5 participants, May 2021]
Modernize Meeting House lighting (pendant, cove, stage) with dimmable/tunable LED strip pendants and wall coves
Whole-house air extraction fan, Meeting House (mold and virus remediation, and hot-weather habitability)
Urgent removal of broken maple tree, limb on CH roof [July 2021]
Replacement of deteriorated kitchen cabinet doors, hinges and knobs [June 2022]
Phase 4
Upkeep: Exterior repairs and painting, Horticulture Plan (in process, partially accomplished)
Outdoor lighting (safety): walkways, wheelchair ramp, Community Hall facade
Re-grading property to allow easy vehicle access to wheelchair ramp and to implement Horticultural Plan
Paint and Repair clapboard exterior of Meeting House. (last painted, 1992). Accomplished: 27 clapboards replaced summer of 2023.
Green Shutters - removed from Meeting House
Storm Windows for stained glass windows: replace (planned 2024)
Foundation stones - mason to patch and repair Meeting house stone foundation
Bell Tower - expose and repair 10” northeast corner beam (planned Summer 2024)
Bell Tower - repair/replace rotted/broken trim pieces; manufacture and install 12 louver panels—tower metal roof is in good condition—(planned Summer 2024)
replace Small Metal Awning over Meeting House Entryway (currently rusted metal). Accomplished: wooden awning rebuilt, new small copper roof fabricated and installed
replace deteriorated railings, Meetinghouse front steps. Accomplished: New iron railings fabricated and installed
Power Wash - wheelchair ramp mold and debris. Accomplished: Power-washed and oil sealed. October 2024
Cellar Door - Community Hall, replace rotted door to crawl space